Tentative construction work scheduled for the remaining portion of the project

Tentative construction work scheduled for the remaining portion of the project will include sidewalk and signal work between Wylie and SR 844/Henderson intersections, painting pavement markings and miscellaneous work throughout the project site. This work relies on weather permitting conditions and will be completed between January and mid-May 2023. Paving of the remaining top course of asphalt between Woodland Avenue and SR 844/Henderson split and also under I-70 parking lot will be completed next April to mid-May 2023.